Skip to main content
Clear icon
71º

TxDOT announces end of year closures for Loop 1604/I-10 interchange project

First flyover ramp is expected to open by end of 2024

SAN ANTONIO – TxDOT has released the holiday construction schedule at the Loop 1604/I-10 interchange.

From now until the end of the year, there will only be one more major closure and two minor closures in the area.

Major Closure:

The weekend of Nov. 15 through 18, one or more highways will be closed in both directions for an extended period, and the ramps may be closed.

Minor Closures:

On the weekends of Nov. 8 through 11 and Nov. 22 through 25, some lanes and ramps will be closed.

One highway may be closed in a single direction, and more extensive closures could be seen overnight.

From Nov. 27 until the end of the year, TxDOT is not planning any closures in the area anymore.

TxDot releases end of year closures schedule for Loop 1604/I-10 Interchange

During the closures that will happen this month, access to businesses will remain open. Law enforcement will be in the area to help assist traffic flow at intersections.

Detailed closure information will be released the week of the closure.

The Loop 1604 Expansion Project:

Since Jan. of this year, construction crews have been working to install flyover ramps at the Loop 1604/I-10 interchange. Steel beam work is 73% complete, with 110 beams in place, according to TxDOT.

The Loop 1604 Expansion Project is an ongoing construction project to help reduce road congestion along 23 miles of Loop 1604 from SH 16 (Bandera Rd. to I-35.

The $1.4 billion project includes expanding the mainlanes from a four to 10-lane expressway, adding HOV (high-occupancy vehicles) lanes, a multi-level interchange at I-10, a new innovative intersection at Blanco Rd. and bicycle/pedestrian accommodations on the frontage roads.

Expected Completion Dates:

  • Segment 1, from SH 16 to I-10, is on schedule to be completed and open to traffic by early 2025.
  • Segment 2, the Loop 1604 and I-10 interchange is scheduled to be completed by 2027. The first flyover ramp is expected to open by the end of 2024.
  • Segment 3, from I-10 to US 281, is scheduled to be completed by the end of 2025.
  • Segment 4, from US 281 to Redland Rd., is expected to be completed by 2028.

About the Author
Halee Powers headshot

Halee Powers is a KSAT producer primarily focused on digital newscasts and events.

Loading...